Concrete piles and foundations | Bin jacking | Corrugated galvanized steel grain storage bins | Smooth wall steel storage bins | Hopper bottom bins | Conveyor tie-ins to existing facilities
Westlock, AB
Westlock Terminals Grain Cleaner
Project Outline
The Westlock terminals facility wanted to add Grain cleaning capabilities which included two gravity cleaners, support tower, and inspection platform, along with 2 grain bins the first being a 21 foot diameter by 60 foot tall Brock E-Series hopper bottom for storing grain prior to cleaning and the second being a 14 foot diameter by 30 foot tall smooth wall Meridian bin for storing the chaff after cleaning.
- Included installation of Multiple Nordstrong Chain conveyors
- Included installation of 2 Nordstrong Bucket elevators
- Included cast in-place concrete foundations for bins, equipment and towers.
Project Challenges
The existing facility had very limited space for the new equipment. The project required modifications to 4 existing bins, including removal of the existing conveyance, filling the existing aeration and unload trenches in bin floors with concrete, then adding raised floors with a new aeration flooring, and installing U-Trough bin sweeps.
- Facility stayed operational during construction.
Project Successes
There were very minimal deficiencies and all were resolved quickly and the systems function as required. The client received their desired outcome at the end of the project.
PROJECT SPECIFICATIONS
Completion Date: December, 2016
END USE
Westlock Terminals Operations
PROJECT SIZE
Roughly 80’ wide by 160’ long
COMPLETION DATE
October 28, 2022
PROJECT DELIVERY METHOD
Shop fabrication, Vendor supplied equipment, on site construction and commissioning
COLLABORATORS
Nordstrong Equipment, BJD Electrical, LV Controls, Rock Solid Concrete