COMMERCIAL BUILDING

Canadian Agri-Blend

Pre-Eng Building | Design-Build

Morinville, AB

Canadian Agri-Blend

Canadian Agri-Blend approached Flynn Bros. Projects in February of 2021 after a fire on the interior of the building had caused significant damage to the structure. While the foundation and concrete flatwork was for the most part still acceptable condition, large pieces of the pre-engineered building were in need of replacement.

After a plan for a new and more resilient structure was approved, it became apparent that existing anchor hold locations and elevations would not be sufficient for the new project. Additionally, due to the elevation of the replacement building and the proximity to the existing building next door, reinforcing of the roof structure of the existing building needed to account for additional drift loading.

By working closely with engineers on the project, Flynn Bros. Projects were able to reinforce the roof by doubling up purlins and bolting reinforcement to the main rafter without interrupting operations in the building, allowing the client to continue to generate revue through what was anticipated to be a disruption.

PROJECT SPECIFICATIONS

Completion Date: TBD

  • Orange icons of two buildings.

    END USE

    Warehouse / Shop

  • An orange icon of a box with arrows on the left side, intersecting at the bottom left corner. One arrow points up, the other points to the right.

    PROJECT SIZE

    16,150 sq ft.

  • An orange icon of a calendar with the last day of the month checked off.

    COMPLETION DATE

    TBD

  • Orange icons of a plane, a truck, and a boat.

    PROJECT DELIVERY METHOD

    Stipulated Price

  • An orange icon of two hands shaking.

    COLLABORATORS

    Trellis Steel, Accurate Plumbing & Mechanical, Gerla Contracting & Electrical Services