COMMERCIAL BUILDING

REFRIGERATIVE SUPPLY LIMITED

PRE-ENG BUILDING WITH STRUCTURAL STEEL MEZZANINE | DESIGN-BUILD | PRECAST INSULATED CONCRETE WALL PANELS | BENDHEIM ARCHITECTURAL GLASS

CALGARY, AB

REFRIGERATIVE SUPPLY LIMITED

Project Outline

Refrigerative Supply Limited in North Calgary needed a new, larger facility, that would accommodate needed warehouse space, and include a training facility, sales floor, and additional office space. The result is a 30,000 sq.ft. Behlen Pre-Engineered Facility with 8,000 sq.ft. of sales and office space on the main floor, and an 8,000 sq.ft. mezzanine that includes training areas, meeting space, and additional offices. The remaining space was designated for warehouse use.

Project Challenges

Installation of the Bendheim glass and coloured glass curtain wall faced unexpected delays. Only one supplier was used for all of the glass in the build. Any replacement curtain wall pieces had to be reordered and shipped from Burnaby, British Columbia, while the Bendheim glass was brought in from overseas.

Project Successes

Despite the delays with product shipments and weather issues, the facility opened on schedule. We were able to adapt the designs to allow for glass installation at a later date, after coordinating the change with site staff, office staff, and subcontractors. This required innovative construction solutions from the Flynn Bros Team by reprioritizing parts of the build to be finished earlier to avoid overall delays in the project deadline.

WAREHOUSE (60%) / OFFICE & SALES (20%) / MEETING & TRAINING AREA (20%)

8,000 SQUARE CONVENTIONAL STEEL MEZZANINE

20' X 20' CANTILEVERED STRUCTURAL STEEL BOARDROOM

ALUMINUM CURTAIN WALL

BENDHEIM ARCHITECTURAL GLASS

SIGNATURE SIGNAGE MONUMENT SPECIFIC TO THE CLIENT

CALGARY, AB

REFRIGERATIVE SUPPLY LIMITED

Project Outline

Refrigerative Supply Limited in North Calgary needed to update their previous facility so they can integrate their warehouse to include a training facility, sales floor, and additional office space. The result is a 30,000 sq.ft. Behlen Pre-Engineered Facility with 7,500 sq.ft. of sales and office space on the main floor, and a 7,500 sq.ft. training area on the mezzanine level. The remaining space was designated for warehouse use. 

Project Challenges

Installation of the glass and coloured curtain wall faced unexpected delays. Only one supplier was used for all of the glass in the build. Any replacement pieces had to be reordered and shipped from Burnaby, Ontario.

Project Successes

Despite the delays with product shipments and weather issues, the facility opened on schedule. We were able to adapt the designs to allow for glass installation at a later date, after coordinating the change with site staff, office staff, and subcontractors. This required innovative construction solutions from the Flynn Bros Team by reprioritizing parts of the build to be finished earlier to avoid overall delays in the project deadline.

PROJECT SPECIFICATIONS

  • A black icon of a calendar with the last day of the month checked off.

    Completion Date - Fall of 2018

  • A black icon of two buildings.

    END USE

    Sales Centre / Warehouse

  • A black icon of a box with arrows on the left side, intersecting at the bottom left corner. One arrow points up, the other points to the right.

    PROJECT SIZE

    30,000 sq ft. Pre-Engineered Facility on 1.71 Acres

  • Black icons of a plane, truck, and transport ship

    PROJECT DELIVERY METHOD

    Design Build, Stipulated Price Contract

  • A black icon of two hands shaking

    COLLABORATORS

    Rick Balbi Architect Ltd.

youtube-video-thumbnail
  • An icon of a black star.

    BUILDING FEATURES

    2 loading docks overhead level

    2 overhead doors grade level

    Sliding door entrance

    2 storey foyer

    29 tf ceiling height in warehouse

    Seminar room on the mezzanine level

    Training facility

    Skylights throughout the building

GET A FREE QUOTE FOR YOUR

COMMERCIAL BUILDING